How Poland’s New Gdańsk Project Changes LNG

Gaz-System has already secured something many European LNG projects do not have before commissioning: customers willing to commit for years. ORLEN has reserved all 6.1 bcm a year of the first Gdańsk FSRU for 15 years, while demand for the second unit exceeded Gaz-System’s original offer strongly enough for the operator to raise its planned capacity from 4.5 bcm to 6.1 bcm a year.[1] Four companies made long-term bookings for that second vessel.[2] The question is therefore no longer whether Poland can build another LNG import route. It is whether those contracts turn Gaz-System into the operator of a heavily used regional transit system rather than the owner of strategically useful spare capacity.

That distinction matters because Poland itself has already completed the larger geopolitical shift. By 2025 it had eliminated Russian oil and gas from its economy after developing Świnoujście LNG, Baltic Pipe and interconnectors with Lithuania and Slovakia.[3] Gdańsk is therefore not another equivalent break with Russian dependence. Its economic case increasingly rests on selling regasification and transmission services into a region beyond Poland’s own demand.

The scale makes that unavoidable. Świnoujście provides 8.3 bcm of annual regasification capacity, the first Gdańsk FSRU is due to add 6.1 bcm from early 2028, and the second unit planned for 2030 would take Polish LNG capacity above 20 bcm a year.[4] At the same time, Polish gas use in power generation is expected to peak around 2030 and then decline as nuclear and renewable capacity expands.[5] The more domestic demand stops growing, the more the economics of the new capacity depend on gas moving through Poland rather than merely arriving there.

Gdańsk’s economics increasingly depend on turning import capacity into regional gas flows



Gaz-System has built that possibility into the project. The first FSRU will connect to the national network through a subsea link and roughly 250 km of new pipelines between Gdańsk and Gustorzyn.[1] The operator has identified Slovakia, Lithuania, Denmark, Germany, the Czech Republic and Ukraine as possible destinations for regasified LNG and has tied its terminal planning to development of the transmission network.[6] Poland and Ukraine are already expanding one of those corridors: their transmission operators agreed to increase capacity toward Ukraine from 15.3 million to 18.4 million cubic meters a day.[7]

The contracts make that export case more credible than a capacity announcement alone. ORLEN’s reservation removes much of the initial demand risk for the first vessel.[1] For the second, demand exceeded the capacity Gaz-System originally offered, and contracted slots reach 47 a year for 2030-2039 and 35 a year for 2040-2044.[2] PGE separately disclosed a 15-year agreement for FSRU 2 services with an estimated financial commitment of about PLN 2.8 billion from commissioning.[8]

But PGE’s disclosure also identifies the boundary between commercial validation and proven earnings. Its PLN 2.8 billion estimate was calculated using indicative tariffs; actual charges will depend on binding tariffs set by Gaz-System and approved by the President of the Energy Regulatory Office.[8] Long-term reservations therefore support the proposition that customers want the capacity. They do not yet establish the revenue, cash generation or return Gaz-System will earn from building and operating it.

Long-term bookings reduce demand risk but do not prove that capacity will translate into earnings



Europe has already provided a warning against treating contracted or installed LNG capacity as synonymous with throughput. At Finland’s Inkoo terminal, restrictions on moving gas south forced sendout down from 87 GWh a day in June 2024 to 32 GWh a day in July.[9] Bottlenecks elsewhere in the Baltic system have produced similar constraints on terminal utilization.[9] The lesson for Gdańsk is specific: regasification capacity only becomes economically valuable at scale when neighboring markets can continuously absorb the gas and the transmission system can deliver it.

Poland has stronger evidence on that point than an isolated terminal project would. Cross-border capacity is being expanded, Gaz-System has explicitly designed the Gdańsk build-out around onward flows, and Europe’s supply mix has moved sharply toward LNG: between 2016 and the first quarter of 2026, eastern gas fell from more than 40% of EU inflows to 5.2%, while LNG rose to 41.7%.[10, 11] European policy also continues to remove Russian gas from the market, with purchases under long-term contracts due to end from January 2027 under the cited measures.[12] Those shifts support a durable role for alternative routes through Poland.

They do not guarantee that Poland captures the traffic. Europe is adding competing import infrastructure at the same time. New LNG terminals began operating in Germany and Italy in 2025, existing facilities in Belgium, Croatia and Italy were expanded, and IEEFA forecasts European LNG import capacity rising another 24% between 2025 and 2030.[13] Gdańsk will therefore enter service in a market where the scarcity being monetized is not simply terminal capacity. It is reliable terminal capacity attached to transmission routes that customers actually nominate and use.

The decisive test is whether booked capacity becomes sustained cross-border throughput



That is why the second FSRU is more consequential than its 6.1 bcm headline suggests. Gaz-System did not approve it solely on a strategic premise: binding demand from four firms followed the open-season process, and excess demand led directly to a larger project.[2, 10] PGE’s 15-year commitment gives part of that demand an observable monetary scale.[8] For Gaz-System, this materially reduces the risk that the asset begins life without customers, but it still leaves the decisive economic variables downstream of the contracts.

The first test arrives after the first FSRU begins commercial service in the first quarter of 2028.[1] If annual throughput approaches its contracted 6.1 bcm capacity and published nominations show meaningful volumes continuing into neighboring markets, the project will have passed the utilization test that Inkoo illustrates can fail even when regasification equipment is available.[1, 9] Gaz-System’s tariff and financial disclosures can then show whether those volumes produce a meaningful revenue and cash contribution, while progress on the second vessel will determine whether the excess demand recorded in 2026 survives through its planned 2030 commissioning.[1, 2]

Until those numbers appear, Poland can credibly claim something narrower and more valuable than another energy-security project: it has found customers for a regional LNG system before that system exists. The unresolved pressure now sits with Gaz-System, because its contracts have reduced demand risk while leaving the harder test untouched — whether booked capacity becomes cross-border throughput at regulated tariffs large enough to show up materially in the operator’s finances.[1, 8]
  1. en.portnews.ru, "GAZ-SYSTEM names first Polish FSRU Solidarity for 2028 Gdansk start-up." Published July 23, 2026. Accessed October 7, 2026.
  2. giignl.org, "Gaz-System gives green light to second Gdansk FSRU terminal." Published n.d.. Accessed October 7, 2026.
  3. European Pravda, "How Poland broke free from Russian gas and why it matters for the EU." Published April 24, 2025. Accessed October 7, 2026.
  4. The Guardian, "Poland’s ‘solidarity’ push for EU energy resilience in face of Russian aggression." Published n.d.. Accessed October 7, 2026.
  5. adlittle.com, "Poland energy outlook, 2026 & beyond | Arthur D. Little." Published n.d.. Accessed October 7, 2026.
  6. LNG Prime, "Poland’s Gaz-System plans Gdansk FSRU terminal capacity boost." Published March 14, 2023. Accessed October 7, 2026.
  7. Reuters, "Poland, Ukraine agreed to increase gas import capacity, energy minister says." Published January 27, 2026. Accessed October 7, 2026.
  8. gkpge.pl, "Signing of an agreement for use of LNG regasification services within Open Season FSRU 2 procedure." Published n.d.. Accessed October 7, 2026.
  9. @ArgusMedia, "Limited interest in Finnish Inkoo LNG slots for 2025 | Latest Market News." Published September 3, 2024. Accessed October 7, 2026.
  10. Riviera, "Poland's Gaz System looks to build second FSRU, third LNG terminal." Published June 24, 2026. Accessed October 7, 2026.
  11. MDPI, "Underground Gas Storage as a Resilience Factor for European Energy Systems During Energy Crises." Published August 20, 2026. Accessed October 7, 2026.
  12. EU Perspectives, "No more exceptions. Europe pushes for a total energy break with Russia - EU Perspectives." Published October 17, 2025. Accessed October 7, 2026.
  13. ieefa.org, "European LNG Tracker." Published n.d.. Accessed October 7, 2026.